6th March 2006
Work started on our house this week, once the water and electricity had been connected.
Both bathrooms have been completely gutted and the builders have started stripping the plaster from the 500 year old walls in the kitchen/family room to reveal the original stone work, which we have asked to be cleaned up and exposed as a feature in the room. The 'grotto' has also been cleared out, ready for renovation at a later date.

Kitchen/Family Room
familyroom8march.jpg

Bathroom two
bathroom18march06.jpg

click here to view floor plan

Inside the Grotto
grotto8march2006.jpg

Outside the Grotto
outsideofthegrotto8march06.jpg

15TH March 2006
 
Work has also started on the outside of the house.
 
The paint work has been stripped and they have started restoring the roof.

Front door
door.jpg

The roof
roof.jpg

The celing in bedroom one & mezzanine level
celing.jpg

What a view !!!!
viewfromwindow.jpg

Week 27 March 2006
 
Works on the house have really started to take off now, the builders have knocked down a wall in bathroom two and built a new wall to extend it.
 
The electrician has also started to completely rewire the whole house, our gas has now been connected and work on installing the central heating system is well underway. 
 

New wall being built to extend bathroom one
newwall.jpg

Week 17th April 2006
 
It has been decided that we will have two bedrooms with on- suite bathrooms instead of three bedrooms. Bedroom one with the very high ceiling also has a mezzanine level which will be turned into another sleeping area once the stairs and banisters are in place.
 
The kitchen has been moved from the large family room, to the front of the house which was the dinning room.
 
This will leave us with a very large family room.

Family Room
livingroom.jpg
To the left is a new wall, with the entrance to bedroom and bathroom two.

Family Room
livingroomkitchen.jpg
Straight ahead is the entrance to the kitchen (what was the dinning room)

Bedroom one
bedroombathroom.jpg
To the right is the entrance to bathroom one. Behind is the mezzanine level in bedroom one

Renovations update 3rd May 2005

 

During our recent trip to Calitri to check out the renovations, we found to our delight that work is well underway and on target to be completed by the end of September.

 

On meeting with Emma from Porta Doriente and Nicola the builder we were able to choose floor and wall tiles, paint for inside and outside the house and also a stair case to join bedroom one with the mezzanine level. It has also been decided that in bedroom one we would have lights in the floor of the mezzanine level that shine upwards, to show off the dome ceiling.

 

Our next visit in August will be to choose furniture.

Restoration of the Fornacella
cooker.jpg

Restoration of the steps leading to bedroom two
steps.jpg

21st June 2006
 
Lastest pictures of our house.
 
The outside of the house has now been painted, and the guttering replaced. Also the floor is ready to be tiled.

Side view of the house & Grotto
italy2.jpg

Preparing the floor
italy1.jpg

Replacement gutter
gutter.jpg
Restoration of features above the front door

Restoration of arch in bathroom two
bathroomarch.jpg

Entrance to cellar from the family room
cellar1.jpg

15th August 2006
 
The floor is starting to take shape and the railings have been put along the mezzanine level.

The finished floor in bedroom two
hpim2996.jpg
This room has fantastic views across the valley

Railings around the mezanine level
hpim2992.jpg

August 2006
 
Just returned from a trip out to Calitri. The house is looking good and should be finished mid October.
 
As the house is rather large it was decided to split the house into two parts, so that smaller parties can rent one side or the other of the house and larger parties could rent the whole house. The central heating has been designed so that only the part of the house that is occupied has the heating switched on.
 
We have chosen the light and bathroom fittings, so the only thing left now is to buy the furniture.

Doorway to bedroom & bathroom two
doorfromlivingroomtobedromandbathroom2.jpg

Entrance to the kitchen
kitchen.jpg

Stairs from bedroom one to the mezanine level
stairs.jpg

Bedroom two
bedroom2.jpg

bathroom two
bathroomtwo.jpg

bathroom one
bathroomone.jpg

24th September 2006
 
Recently received some new photo's of the house which shows how close our house is to being finished. With the walls plastered and painted the original exposed rocks (approximately 500 years old) really stand out, we are really pleased with the look that we have achieved.  
 
 

Restoration to the Front Door
septemberphotoone.jpg

Bedroom two
septemberphotothree.jpg

This will be the kitchen.
septemberphotofour.jpg

Archway from the living room to bedroom two
septemberphotosix.jpg

The livingroom
septemberphototwo.jpg
One of the tradesmen restoring the front door

14th October 2006
 
Just returned from Calitri, the building work is completed.
 
On this trip we have purchased a kitchen which should be fitted within the next couple of weeks.
 
We are back in Italy at the end of November to purchase furniture to complete this project.

Entrance Hall
entrancehallone.jpg

Entrance Hall
entrancehalltwo.jpg

Stairway
stairway.jpg

Skylight in the livingroom
skylightinlivingroom.jpg

Bathroom one
bathroomone2.jpg

Bathroom two
bathroomtwo4.jpg

bathroom one
newbathroomone.jpg

The Kitchen Fitting
finishedkitchen3.jpg

finishedkitchen2.jpg